Maersk Nomad Conversion

Delivery year 2012
Project name Maersk Nomad
Concept Conversion from PSV to construction vessel
Yard Yiu Lian Dockyards Ltd, China

With just 150 days allowed, Callenberg Technology Group carried out a complete conversion from a PSV to a construction vessel on board Maersk Nomad at Yiu Lian Dockyards in China.

 Callenberg Technology Group handled the entire electrical installation from project management and engineering to electrical installation and commissioning on board the vessel.

16 different areas were included in scope, including helideck, bridge extension, a new accommodation module and new lifeboats.

  • 150 days in the yard
  • 22+ Callenberg team of project managers, engineers, fitters, electricians and smiths
  • 70+ different works

 

http://callenberg.com/wp-content/uploads/2015/09/thumbnails/maersknomad-31364-1400x.jpg

Technical details

  • Helideck
  • New accommodation module
  • Bridge extension
  • Crane
  • Lifeboats FRC boats
  • ROV garage
  • New engine room with new D/G’s
  • HiPAP
  • Heeling System
  • MSB upgrade with new breakers
  • PMS upgrade
  • Alarm & control system upgrade
  • FD system upgrade
  • MSB for new D/G’s
  • Starters for aux equipment
  • Design & documentation