HVAC for Eldfisk 2/7s Process and LQ

Delivery year 2012 - 2013
Project name Eldfisk 2/7s process and LQ
Concept Wellhead platform
Operator/ Client Conoco Phillips

Callenberg Technology Group supplied HVAC equipment to the new integrated wellhead, process and 154-bed living quarters platform. The platform is bridge linked to the Eldfisk complex.

The scope of work included detailed design, procurement and equipment delivery.

HVAC equipment supplied included Air Handling Units, Fans, kitchen extract hoods, central vacuum cleaning system, self-contained units, fan coil units, all type of dampers, field instrumentation, sound attenuators, electric heating coils, intake and exhaust louvers.

http://callenberg.com/wp-content/uploads/2015/01/thumbnails/eldfisk-14996-400x.jpg